Weekly Update, January 06, 2012
Remedial Investigation field work commenced in late-March 2010 at the former Metropolitan Works MGP as part of the New York State Department of Environmental Conservation (NYSDEC)- approved Remedial Investigation Work Plan (RIWP). The completed work included the installation of soil borings, monitoring wells, test pit excavations, and indoor air and sub-slab soil vapor points to gather information required to determine the nature and extent of impacts at the former Metropolitan Works MGP. Drilling proposed in RIWP Addendum No. 2 was completed in April 2011. Additional work to complete the Remedial Investigation, including RIWP Addendums No. 1 and No. 3, is scheduled for the fall of 2011.
Activities Week of January 2 – January 6:
- No field activities performed.
Future (two week look - ahead) activities:
- No field activities scheduled.