Weekly Update, August 06, 2010
Remedial Investigation field work commenced in late-March at the former Metropolitan Works MGP as part of the New York State Department of Environmental Conservation (NYSDEC)-approved Remedial Investigation Work Plan (RIWP). The work includes the installation of soil borings, monitoring wells, test pit excavations, and indoor air and sub-slab soil vapor points to gather information required to determine the nature and extent of impacts at the former Metropolitan Works MGP.
Activities Week of July 26– July 30:
- Performed well gauging of all newly installed wells.
Future (two week look - ahead) activities:
- No activities planned