Weekly Update, May 28, 2010
Remedial Investigation field work commenced in late-March at the former Metropolitan Works MGP as part of the New York State Department of Environmental Conservation (NYSDEC)-approved Remedial Investigation Work Plan (RIWP). The work includes the installation of soil borings, monitoring wells, test pit excavations, and indoor air and sub-slab soil vapor points to gather information required to determine the nature and extent of impacts at the former Metropolitan Works MGP.
Activities Week of May 24– May 28:
- Completed asphalt surface restoration of test pits at two locations.
Future (two week look - ahead) activities:
- Continue with remedial investigation field activities, including soil boring pre-clearing, soil boring advancement, and groundwater monitoring well installation at one remaining location adjacent to the canal.
- Well development at all newly installed wells to facilitate groundwater sampling.